Setting for the Work Plan Cleaning Cleaning Area Sequence

Currently there does not appear to be a way to change the work plan cleaning area sequence. The Wiki page describe this setting as “Cleaning area sequence in a plan (top area cleaned first)” which sounds like it follows in the order of area creation. It would be nice to be able choose the order of operation. Thank You Cookie

Welcome to the community.

You can change the order of the areas in the work plan edit screen. There are “drag handles” on the right of the area names.

5 Likes

Thank you Ken. Try did try the drag handle before posting they did seem to work. Now that you have show they do indeed move area try them again and voila they work. Again thank you.

Richard

2 Likes

Glad it works for you now!