My municipality does not allow to use heavy machinery including electric snow blowers from 8pm - 8am. Not matter if it is snowing hell.
Auto schedule will program itself at any time at night if it is snowing so without the option to not auto schedule from x to y, I cannot really use it and risk it running at night.
3 Likes
Hi there, thanks for bringing this to our attention. We haven’t considered this aspect before. If more users share the same concern, I’ll pass it along to our product team for further consideration.
2 Likes
I think there is interest. I do think this is a much needed feature for all modules. Quiet hours is important in a lot of communities.
I have a field where the plan shows it will take 25 hours. I don’t want it mowing at night. How do I have it mow from 6a - 9p Tues and Wed? Is this the proper way to set it so it will resume the following morning at 6a, or is what I’m wanting to do not possible and you have to split it by zones to fit in the desired window?
[image]
If this can’t be done, can we switch this topic to feature requests/ideas?
This request is huge. Where I am at, it can get well into the 100’s and I would like to have the rover only cut during certain hours. What makes this challenging for me is the times would vary based on the module.
EX:
Mower is quiet. It could cut from 6am until 11am. Then resume around 7pm to 9pm.
Blower not quiet. I would restrict this to 8am to 11am and resume 7pm-8pm in the hot months
Start a plan, pause the plan and run the rover manually for some time, then tell the rover to continue the…
I don’t have see if it’s possible to define working hours.
Don’t mowing from 8pm to 10 am for example.
It could be great if it’s also possible to have this on each zone. in order to do shadow zone in the afternoon not in the morning with the dew
Got awakened by family in the middle of the night complaining that “my” Yarbo was mowing, making noise and disturbing people.
Turns out that last night, Yarbo was on its dock charging when the task schedule end time hit, ignored it and resumed its work plan when battery level reached 80%.
Work plan got manually canceled in a hurry to restore peace, now I have no way to know where it stopped and where to resume as work history has been missing from the app since the last “upgrade”
I…
2 Likes